Navigating the Legal Landscape: A Legal Perspective on EPU's Real Estate Acquisition Guidelines
- Shareen Ng En Yi
- Mar 1, 2024
- 4 min read
In recent headlines, there has been a notable surge in news surrounding companies securing Engineering, Procurement, and Construction (“EPC”) contracts, prompting many to inquire about their significance and intricacies.
What is an EPC Contract?
EPC contract has traditionally been the most common form of contract used to undertake construction and engineering works by the private sector on large-scale, complex infrastructure projects across various industry sectors, including power, oil and gas, transport, water and waste. Essentially, an EPC contract is a comprehensive agreement that encompasses the entire project lifecycle, from initial design and procurement to construction and commissioning. Under an EPC contract, contractors are typically obliged to deliver a complete facility to the project company on a turnkey basis (the project company need only "tum a key" to start operating it). As such, the terms EPC or turnkey are often used interchangeably.
Key Features of an EPC Contract
The key features of an EPC contract are, inter alia, as follows:
Fixed Price: EPC contract often involves a fixed price for the entire scope of work with limited ability for the contractor to claim additional amounts. This provides certainty to the project owner regarding project costs, although it may shift some risks to the contractor.
Time-bound Schedule: EPC contract includes a schedule for project completion, with specific milestones and deadlines with limited ability for the contractor to claim an extension of time ("EOT").
Single Point Responsibility: The contractor (often referred to as the EPC contractor) is responsible for all aspects of the project, including design, procurement of materials and equipment, construction, commissioning, and handover to the project owner.
Guaranteed Performance: EPC contractor often provides performance guarantees, ensuring that the completed project meets specified criteria such as performance standards, functionality, and operational efficiency.
Key Issues of an EPC Contract
Parties to an EPC contract shall consider the key practical, legal and commercial issues when negotiating an EPC contract including but not limited to the followings:
Pricing and payment mechanism
An EPC contract will typically be priced under the lump sum method. Under lump sum pricing, the EPC contractor agrees to complete all of the works required to deliver the project for a single "lump sum" price. The EPC contractor therefore bears the risk of cost overruns, including the risk of changes in the quantities or work from those which it may have originally identified. On the other hand, if the cost of the works is less than the lump sum price, it will benefit from the savings. As this type of pricing method apportions more risk to the EPC contractor, the EPC contractor shall assess the actual amount of labour and materials used and how external factors, such as ground and weather conditions, may affect the level or type of work when negotiating the EPC contract.
Notwithstanding the above, a lump sum contract does not apportion all the project risk to the EPC contractor and the EPC contract will contain mechanisms that operate to vary the contract price in certain circumstances, for example, variations to the scope of the works.
Limitations on liability
A typical EPC contract limits the contractor's liability in several different ways. This is an important aspect of risk allocation between the project owner and the EPC contractor and allows the EPC contractor to properly price the risk elements under the EPC contract and negotiate a commercially realistic contract price. It is unrealistic to expect a contractor to accept unlimited liability and most EPC contractors will not enter into a contract with uncapped liability as a matter of policy. In practice, caps on liability under an EPC contract are heavily negotiated
Varying the scope of work
In construction projects, it is often a source of dispute whether a communication to the contractor is an instruction to comply with the contract or a variation to the scope of work. As such, the EPC contract typically includes a formal variation procedure. This differs from contract to contract but typically addresses:
the form of a variation instruction usually this must be in writing and identify as a variation instruction.
whether variations can be instructed only by the project owner or whether the EPC contractor can also propose variations. This may be permitted only if it improves the quality, efficiency or safety of the works. In any case, the project owner always has the right to accept or reject any EPC contractor-proposed variation.
whether the time and cost consequences of a variation must be agreed in advance of the EPC contractor being obliged to carry out the varied works.
Additionally, variations are usually expensive, resulting in both increased cost and delay and disruption to the works. Valuing variations is therefore a key aspect of any EPC contract. Often the parties will pre-agree rates or prices for items of varied work that are set out in a schedule to the EPC contract. In the absence of pre-agreed rates or prices, the varied works may be valued on the basis of actual cost plus a pre-agreed margin (to cover profit and overheads).
Disputes
A typical EPC contract adopts a tiered approach to dispute resolution. It is important that the EPC contract is clear whether each stage of the dispute avoidance/resolution process is mandatory or optional and, if mandatory, that time limits are imposed at each stage so that the dispute can be referred to the next stage if it is not resolved. This approach may include combination of the following processes:
negotiation between senior management of each of the parties:
mediation;
arbitration; and/or
statutory adjudication under Construction Industry Payment and Adjudication Act 2012.
By considering the key issues as set out above during the drafting and negotiation of an EPC contract, parties can minimize potential conflicts, clarify expectations, and increase the likelihood of a successful project outcome. Ultimately, a well-drafted and negotiated EPC contract serves as a blueprint for project execution, guiding stakeholders through every stage of the process from inception to completion. As projects become increasingly complex and globalised, the importance of robust contractual arrangements cannot be overstated.


